At the last ASHRAE meeting in January, the 90.1 committee 
approved a second public review of draft Addenda e 
(Appendix G) titled "Performance Rating Method".  The draft 
addenda needs to be approved by another committee in ASHRAE 
this spring before it is made available for public comment 
which will hopefully happen early this summer.  At that 
time, the addenda will be available on the ASHRAE web site. 
 
If you are interested in Appendix G you may want to join 
the 90.1 "unofficial" mailing lists that we host for the 
full committee and ECB subcommittee.  Just send blank e-
mails to:

  SSPC901L-subscribe at gard.com

and

  901ECB-subscribe at gard.com

These will allow you to be notified of conference calls as 
well as seeing discussion regarding these committees.

Jason
Chair of 90.1 ECB

On 11 Mar 2003 at 13:16, Lamar Henderson wrote:

> Where can a copy of the draft be found and is there a
> general time frame "soon."
> 
> Lamar Henderson
>   -----Original Message-----
>   From: postman at gard.com [mailto:postman at gard.com]On Behalf
>   Of Gowri,
> Krishnan
>   Sent: Tuesday, March 11, 2003 12:19 PM
>   To: BLDG-SIM at GARD.COM
>   Subject: [BLDG-SIM] Status of BSR/ASHRAE/IESNA Addendum e
>   to ASHRAE 90.1-
> 2001 as Informative Appendix G
> 
> 
>   Appendix G is not approved yet.  A second public review
>   draft will be
> available soon.  Jason Glazer would be able to give you more
> definitive answer on when the second draft will be
> available.
> 
>   - krishnan, PNNL
>     -----Original Message-----
>     From: Tianzhen Hong [mailto:thong at eley.com]
>     Sent: Monday, March 10, 2003 3:23 PM
>     To: BLDG-SIM at GARD.COM
>     Subject: [BLDG-SIM] Status of BSR/ASHRAE/IESNA Addendum
>     e to ASHRAE
> 90.1- 2001 as Informative Appendix G
> 
> 
> 
> 
>     The BSR/ASHRAE/IESNA Addendum e to ASHRAE 90.1- 2001 as
>     Informative
> Appendix G was available for public review in July 2002, can
> someone update me its status? Whether it is officially
> approved or under another review?
> 
>     The new appendix supposes to provide more clear
>     methodology for
> performing LEED Energy and Atmosphere Credit 1 - Optimize
> Energy Performance calculations.
> 
> 
>     Thanks
> 
>     Tianzhen
> 
> 
> 
> ==================
> You received this e-mail because you are subscribed
> to the BLDG-SIM at GARD.COM mailing list.  To unsubscribe
> from this mailing list send a blank message to
> BLDG-SIM-UNSUBSCRIBE at GARD.COM
> 
> 
> ======================================================
> You received this e-mail because you are subscribed 
> to the BLDG-SIM at GARD.COM mailing list.  To unsubscribe from
> this mailing list send a blank message to
> BLDG-SIM-UNSUBSCRIBE at GARD.COM


=========================================================
Jason Glazer, P.E.  jglazer AT gard DOT com  847 698 5686
GARD Analytics - http://www.gard.com/
1028 Busse Highway, Park Ridge, IL 60068
Building Energy Simulation and Analysis
Admin of BLDG-SIM list for building simulation users

======================================================
You received this e-mail because you are subscribed 
to the BLDG-SIM at GARD.COM mailing list.  To unsubscribe 
from this mailing list send a blank message to 
BLDG-SIM-UNSUBSCRIBE at GARD.COM



More information about the Bldg-sim mailing list