[BLDG-SIM] Steam and Chilled Water Meters

Vikram Sami VSami at lasarchitect.com
Fri Feb 23 11:58:10 PST 2007


I'm modeling a project for LEED ECB compliance for a campus facility
that has district chilled water and steam. Having never used the chilled
water and steam meter functions before in eQUEST, I'm wondering if
anyone can give me some pointers on things to watch out for. How do you
document this in the ECB report? The steam & Chilled water meters only
give you a BTU output, and no dollar values. 

Any advice would be appreciated.

Thanks in advance. 

Vikram Sami, LEED AP
Direct Phone 404-253-1466 | Direct Fax 404-253-1366

LORD, AECK & SARGENT ARCHITECTURE
Responsive Design * Technological Expertise * Exceptional Service
www.lordaecksargent.com




===========================
You received this e-mail because you are subscribed 
to the BLDG-SIM at GARD.COM mailing list.  To unsubscribe 
from this mailing list send a blank message to 
BLDG-SIM-UNSUBSCRIBE at GARD.COM
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.onebuilding.org/pipermail/bldg-sim-onebuilding.org/attachments/20070223/efd8ef2b/attachment.htm>


More information about the Bldg-sim mailing list