We are working on a project in Georgia that is served by Georgia Power. Their utility rate is structured as below.
In eQUEST, the problem arises because there is a an energy tier within a kWh/kW tier. eQUEST will not let the Step Size in the KWH/KW Block Charge.
How do you set different kWh limits within a set kWh/kW hours?
There was a previous thread on this subject in 2004, but nothing came out of it for eQUEST, as the recommended flag schedule is not what this rate is asking for. http://lists.onebuilding.org/htdig.cgi/bldg-sim-onebuilding.org/2004-March/001493.html
Any help would be appreciated.
Thanks,
Dana
All consumption (kWh) not greater than
200 hours times the billing demand:
First 3,000 kWh................................................................... at .................................10.8471¢ per kWh
Next 7,000 kWh................................................................... at ...................................9.8355¢ per kWh
Next 190,000 kWh............................................................... at ...................................8.3880¢ per kWh
Over 200,000 kWh.............................................................. at ...................................6.4648¢ per kWh
All consumption (kWh) in excess of 200
hours and not greater than 400 hours
times the billing demand...................................................... at ...................................1.1062¢ per kWh
All consumption (kWh) in excess of 400
hours and not greater than 600 hours
times the billing demand...................................................... at ...................................0.8730¢ per kWh
All consumption (kWh) in excess of 600
hours times the billing demand........................................... at ...................................0.6292¢ per kWh
Dana Troy
Energy Analyst
LEED® Accredited Professional
<http://www.glumac.com/>
________________________________
320 SW Washington, Suite 200
Portland, OR 97204-2640
T. 503.227.5280 F. 503.274.7674
Thinking. Inside the building.
www.glumac.com <http://www.glumac.com/>
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.onebuilding.org/pipermail/bldg-sim-onebuilding.org/attachments/20090608/fb6027f3/attachment-0002.htm>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: not available
Type: image/gif
Size: 50453 bytes
Desc: image001.gif
URL: <http://lists.onebuilding.org/pipermail/bldg-sim-onebuilding.org/attachments/20090608/fb6027f3/attachment-0004.gif>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: not available
Type: image/gif
Size: 1425 bytes
Desc: image002.gif
URL: <http://lists.onebuilding.org/pipermail/bldg-sim-onebuilding.org/attachments/20090608/fb6027f3/attachment-0005.gif>
More information about the Bldg-sim
mailing list