[Bldg-sim] LEED-NC - Hospital Overbuild

Ryan Schmidt RSchmidt at Horizon-Engineering.com
Thu Sep 3 06:29:54 PDT 2009


I am currently working on performing an Energy Model for a Hospital
addition that will be credited under LEED-NC. The project includes a
renovation of third and forth floors (LEED-CI) and construction of a new
fifth floor and mechanical equipment room that will serve all three
floors. I am having trouble determining an approach for modeling the
EAc1 mechanical systems for the isolated fifth floor model and
accounting for primary mechanical equipment which consists of an
assortment of existing hydronic systems throughout the hospital. I
understand this is quite vague but any guidance will be greatly
appreciated.

 

Thanks in advance,

 

Ryan G. Schmidt

Horizon Engineering Associates, Field Engineer

rschmidt at horizon-engineering.com
<mailto:rschmidt at horizon-engineering.com> 

704.523.5354 (t)

704.523.5347 (f)

252.622.9606 (m)

 

-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.onebuilding.org/pipermail/bldg-sim-onebuilding.org/attachments/20090903/62f9716b/attachment.htm>


More information about the Bldg-sim mailing list