John,

Having completed numerous LCCA and economic feasibility studies we've also tried to find this sort of information and have found it in short supply.  As Jeremy noted RS Means can serve as a source, albeit a limited one, especially for the many "advanced" systems being evaluated for projects (i.e. chilled beams, VRF, geo, etc.).  Vendors and our clients' maintenance staffs tend to be the most reasonable sources, though there are some challenges there as well.



It would be great to find a more robust O&M cost data set that's publicly shared, especially with data from the likes of BOMA and GSA.  In the meantime, in lieu of having a high level of confidence with numbers you're finding, I would suggest a sensitivity analysis around the O&M costs to help gauge the impact and provide the basis for a "risk & reward" conversation with your client.



Regards,

Paul

Paul Erickson  LEED(r) AP BD+C
Sustainable



AEI | AFFILIATED ENGINEERS, INC.
5802 Research Park Boulevard | Madison, WI  53719

P: 608.236.1112 | F: 608.238.2614
perickson at aeieng.com<mailto:perickson at aeieng.com>  |  www.aeieng.com<http://www.aeieng.com>







-----Original Message-----
From: bldg-sim-bounces at lists.onebuilding.org [mailto:bldg-sim-bounces at lists.onebuilding.org] On Behalf Of Jeremy Poling
Sent: Tuesday, June 14, 2011 12:59 PM
To: Eurek, John S NWO; bldg-sim at onebuilding.org
Subject: Re: [Bldg-sim] Life Cycle Cost Analysis (UNCLASSIFIED)



RS Means has a "Facilities Maintenance & Repair Cost Data Book"

available at http://rsmeans.reedconstructiondata.com/CostBooks.aspx.

Otherwise, you could possibly contact your local BOMA affiliate to see

if they have general data they are willing to share on these.



Jeremy R. Poling, PE, LEED AP+BDC



-----Original Message-----

From: bldg-sim-bounces at lists.onebuilding.org

[mailto:bldg-sim-bounces at lists.onebuilding.org] On Behalf Of Eurek, John

S NWO

Sent: Tuesday, June 14, 2011 12:55 PM

To: bldg-sim at onebuilding.org

Subject: [Bldg-sim] Life Cycle Cost Analysis (UNCLASSIFIED)



Classification: UNCLASSIFIED

Caveats: NONE



Group,



After doing the energy model of two different systems I was asked to do

a

life cycle cost analysis.



I am able to look up every needed value (equipment cost, equipment life,

installation cost, energy cost, inflation rate, fuel costs.)



I can site where I got each number. (right or wrong, I have the source.)



The only missing number is operation and maintenance costs.  Where can I

look

up O&M and site the source?



I am comparing a geo-thermal system with a boiler/chiller system.











"Freedom is a small price to pay to stop Global Warming."



John Eurek PE, LEED AP



Classification: UNCLASSIFIED

Caveats: NONE





_______________________________________________

Bldg-sim mailing list

http://lists.onebuilding.org/listinfo.cgi/bldg-sim-onebuilding.org

To unsubscribe from this mailing list send  a blank message to

BLDG-SIM-UNSUBSCRIBE at ONEBUILDING.ORG





_______________________________________________

Bldg-sim mailing list

http://lists.onebuilding.org/listinfo.cgi/bldg-sim-onebuilding.org

To unsubscribe from this mailing list send  a blank message to BLDG-SIM-UNSUBSCRIBE at ONEBUILDING.ORG
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.onebuilding.org/pipermail/bldg-sim-onebuilding.org/attachments/20110614/2ad00a3e/attachment-0001.htm>


More information about the Bldg-sim mailing list