Hi,

I am doing the LEED v3 EA credit for a large office building with a data center and wanted to see if anyone had any experience with this and knew what the baseline should be.  In particular I wanted to know what standards (if any) there are for the following issues:


-       IT load schedule (is it flat or staggered as in the proposals to 90.1 2010 and Title 24 2011)?

-       CRAC/CRAH unit fans, is the basecase constant speed?

-       Hot aisle containment, can you take credit for higher DT, lower airflow?  If so, what is the baseline DT?

-       Air and water-side economizers can you omit them in the baseline?

-       CHW plant equipment, can you use a model that just meets the mandatory minimum equipment efficiencies?

Also, if anyone has reviewed any of the CIRs on this issue and has a cheat sheet of CIRs that would be helpful.

Thanks in advance,

Rupam Singla, P.E.
Mechanical Engineer, Taylor Engineering, LLC
1080 Marina Village Parkway, Suite 501, Alameda CA 94501
(510) 473-1172 direct, (510) 749-9135 office
(510) 749-9136 fax, (513) 254-3454 mobile
rsingla at taylor-engineering.com<mailto:rsingla at taylor-engineering.com>
www.taylor-engineering.com

-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.onebuilding.org/pipermail/bldg-sim-onebuilding.org/attachments/20120320/69e80710/attachment.htm>


More information about the Bldg-sim mailing list