[Bldg-sim] Four orientations for new construction attached to existing buildings?

Bishop, Bill bbishop at pathfinder-ea.com
Thu May 30 07:54:37 PDT 2013


Thanks Jim, Stormy.

The project doesn't seem to meet the definition/intent of "addition". It has independent MEP systems and it doesn't share any structural elements with the two other dorms that it is connected to. It just has doors in the stairwells that allow access to the central corridors of the adjacent two dorms.

Nevertheless, I will skip the baseline rotations and let the LEED Reviewer tell me otherwise.

~Bill

From: Stormy L. Shanks [mailto:shankssl at kjww.com]
Sent: Thursday, May 30, 2013 10:22 AM
To: Bishop, Bill; Building SimForum
Subject: RE: [Bldg-sim] Four orientations for new construction attached to existing buildings?

Hi, Bill - I had this situation once, and I rotated the baseline and submitted it. I got the following comment:

Table 1.8.1 and Table 1.8.1(b) of the template include the simulation results for the 90-degree, 180-degree, and 270-degree Baseline model rotations; however, since this project is an addition to an existing project, the Baseline model must not be simulated for the different rotations. Revise Table 1.8.1 and Table 1.8.1(b) by excluding the results for the 90-degree, 180-degree, and 270-degree Baseline model rotations.


[cid:image001.png at 01CE0924.38506AB0]

Stormy L. Shanks, PE
Mechanical Engineer

2882 106th St, Des Moines, IA 50322

web<http://www.kjww.com/> | Facebook<http://www.facebook.com/kjwwengineering> | Twitter<http://twitter.com/kjww> | LinkedIn<http://www.linkedin.com/company/kjww-engineering-consultants>



From: bldg-sim-bounces at lists.onebuilding.org<mailto:bldg-sim-bounces at lists.onebuilding.org> [mailto:bldg-sim-bounces at lists.onebuilding.org] On Behalf Of Bishop, Bill
Sent: Thursday, May 30, 2013 9:06 AM
To: Building SimForum
Subject: [Bldg-sim] Four orientations for new construction attached to existing buildings?

A new dorm is physically connected to two existing buildings. Do I do four rotations for LEED modeling?

Thanks,
Bill


William Bishop, PE, BEMP, BEAP, LEED AP | Pathfinder Engineers & Architects LLP
Senior Energy Engineer

134 South Fitzhugh Street                 Rochester, NY 14608
T: (585) 325-6004 Ext. 114            F: (585) 325-6005
bbishop at pathfinder-ea.com<mailto:wbishop at pathfinder-ea.com>           www.pathfinder-ea.com<http://www.pathfinder-ea.com/>
P   Sustainability - the forest AND the trees. P

P.S. The world's first car accident occurred this day in 1896. Henry Wells hit a bicyclist in NYC.


________________________________
This message and any attachments contain information intended for a specific party and may include sensitive or confidential material. If you are not the intended recipient, please do not read, copy, use, or disclose to others. Please notify the sender of the delivery error by reply and then permanently delete this message and all attachments.
  
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.onebuilding.org/pipermail/bldg-sim-onebuilding.org/attachments/20130530/17029d8a/attachment-0002.htm>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image001.png
Type: image/png
Size: 9229 bytes
Desc: image001.png
URL: <http://lists.onebuilding.org/pipermail/bldg-sim-onebuilding.org/attachments/20130530/17029d8a/attachment-0002.png>


More information about the Bldg-sim mailing list