[Equest-users] Editing External lighting Schedule

Matutinovic, Luka LMatutinovic at halsall.com
Fri Jul 10 07:02:37 PDT 2009


I had limited success in editing the Wizard schedules by adjusting the max and min thresholds on the vertical axis and the start and end hours along the top axis.  My understanding is that eQuest generates those schedules based on the building type definition at the beginning of the shell wizard.  I had many headaches trying to edit the schedule after I realized I selected the wrong building type, especially when dealing with multiple shells. I inevitably end up using John's approach once in the detailed mode.

When people are creating models for LEED, do you use the schedules found in the back of the 90.1 User's Manual, or do you create your own schedules?  How has the USGBC reviewed this issue since according to App G, schedule creation is up to the designer and the "rating authority"?  It would seem to me that the USGBC wouldn't care as long as you use schedules that are reasonable for the building type and anticipated operation, and that the reference building uses the same ones (unless daylight controls or demand controlled ventilation is being dealt with through schedules and not simulation software directly). 

Any thoughts?

Thanks,
Luka Matutinovic

-----Original Message-----
From: equest-users-bounces at lists.onebuilding.org [mailto:equest-users-bounces at lists.onebuilding.org] On Behalf Of John Aulbach
Sent: Friday, July 10, 2009 1:47 AM
To: equest-users at lists.onebuilding.org; nate murray
Subject: Re: [Equest-users] Editing External lighting Schedule


Nate:

The only way I know to edit such schedules is to change the mode to Detailed Edit, then make the schedule changes.

If you try to go back to the Wizard mode, those changes will be deleted.

John Aulbach

--- On Thu, 7/9/09, nate murray <natemurr at gmail.com> wrote:

> From: nate murray <natemurr at gmail.com>
> Subject: [Equest-users] Editing External lighting Schedule
> To: equest-users at lists.onebuilding.org
> Date: Thursday, July 9, 2009, 5:59 PM
> Hi,
> I want to make the external lighting schedule so that there is a 
> little bit smaller loads in april and october then the rest of the 
> months. I see the monthly profiles on the External lighting screen in 
> Design Wizard, but how do I go about editing those monthly 
> profiles...if that's what I should do.
> 
> 
> Thanks,
> --
> Nathan Murray
> 
> 
> 
> -----Inline Attachment Follows-----
> 
> _______________________________________________
> Equest-users mailing list
> http://lists.onebuilding.org/listinfo.cgi/equest-users-onebuilding.org
> To unsubscribe from this mailing list send  a blank message to 
> EQUEST-USERS-UNSUBSCRIBE at ONEBUILDING.ORG
> 


      
_______________________________________________
Equest-users mailing list
http://lists.onebuilding.org/listinfo.cgi/equest-users-onebuilding.org
To unsubscribe from this mailing list send  a blank message to EQUEST-USERS-UNSUBSCRIBE at ONEBUILDING.ORG



More information about the Equest-users mailing list