Hi Mary,

Actually this is pretty easy. You can select packaged VAV as your system and
then when you are in the detailed edit mode go to your HVAC tab, then to the
Air-Side HVAC System Parameters tab, then to the cooling tab, and lastly to
the Stages tab at the far right. That should work for you. If you have a ME
that you are working with a few questions to her would help as to which
option to choose. A good vendor can help with this, too.

Let us know if ya need any more help.

Regards,
Carol

On Fri, May 7, 2010 at 7:14 AM, Mary Wyllie <MWyllie at hiscutt-aia.com> wrote:

>  Does anyone have experience modeling multi-stage air volume roof top
> units such as the Lennox Energence?  Do I handle that as a VAV or stick with
> constant volume and try and model it with schedules?  And, yes, I’m an
> architect trying to do an engineer’s job, so be gentle with me.  I’ve
> already learned so much from reading all of your posts over the last few
> months.
>
>
>
> *Mary Wyllie | AIA | LEED AP*
>
> Associate
>
> Hiscutt & Associates, Inc.
>
> 3655 Brookside Pkwy., Suite 575
>
> Alpharetta, GA 30022
>
> (770) 753-8787
>
>
>
> *R**educe **R**euse **R**ecycle **ü*
>
>
>
> _______________________________________________
> Equest-users mailing list
> http://lists.onebuilding.org/listinfo.cgi/equest-users-onebuilding.org
> To unsubscribe from this mailing list send  a blank message to
> EQUEST-USERS-UNSUBSCRIBE at ONEBUILDING.ORG
>
>
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.onebuilding.org/pipermail/equest-users-onebuilding.org/attachments/20100511/6906dad6/attachment-0001.htm>


More information about the Equest-users mailing list