[Equest-users] pool heating baseline system

Pasha Korber-Gonzalez pasha.pkconsulting at gmail.com
Tue Jan 25 14:49:38 PST 2011


Isn't the pool heating system considered as a process load for 90.1 since it
has no effect on the overall building design?  It would be exactly the same
in the baseline as it is for the proposed case.

...just a thought, although I haven't run into this scenario with any of my
sim projects.

Pasha


On Tue, Jan 25, 2011 at 3:19 PM, Mirza Sajjal <ms2995 at gmail.com> wrote:

> Can anyone tell me what the baseline pool heating system should be if the
> design calls for heat pumps? Per App. G Table G3.1.11 the requirement is
> that the energy source be the same, in this case electricity. Can we model
> the baseline as electric water heaters or should the system type (heat
> pumps) also remain the same in the baseline since electric resistance pool
> heating is unconventional? Theres a huge energy savings difference between
> the two baselines and was wondering how others have modeled this in terms of
> LEED.
> Your opinion and insight is much appreciated.
> Thanks in advance for any response.
>
> Mirza
>
> _______________________________________________
> Equest-users mailing list
> http://lists.onebuilding.org/listinfo.cgi/equest-users-onebuilding.org
> To unsubscribe from this mailing list send  a blank message to
> EQUEST-USERS-UNSUBSCRIBE at ONEBUILDING.ORG
>
>
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.onebuilding.org/pipermail/equest-users-onebuilding.org/attachments/20110125/db63cbb2/attachment-0001.htm>


More information about the Equest-users mailing list