[Equest-users] Default value and other questions

Chen, Ke-Huang kehuang.chen at siemens.com
Sat Nov 26 19:09:42 PST 2011


Hi all,
 
I am building a model for LEED project and I have some questions
confused me for a long time, does anybody know the answers or can give
me some suggestions?
 
1. All the property information I have is only a part of all the
information listed in eQUEST, if I can't find the information in
equipment spec., could I leave it in default value or I need to find out
anyway? If I leave it in default value, will it effect the result a lot?
 
2. The area is 19211 ft2 in document and I import the Building Area
19211 ft2 in wizard screen 1 of 25, but after I footprint the shape with
CAD file, there is an information "Dimensions Specified Above: 17775
ft2". Does it mean the area of this building now is 17775 ft2 not 19211
ft2? Will it be accepted if the building area is not the same as the
document?
 
3. The reference guide shows the process energy should be at least 25%
of all energy cost. If the process energy is less than 25% after I
finish building the model, how could I increase the process energy to
25%?
 
 
Thanks for any help.
 
 
 
 
KeHuang Chen
System Engineer
IC BT Division
Siemens Limited Taiwan
 
Tel : (+886)2-2652-8888 ext. 896
Mobile : (+886)960548011
Fax : (+886)2-2652-8824
 
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.onebuilding.org/pipermail/equest-users-onebuilding.org/attachments/20111127/03e9dd32/attachment.htm>


More information about the Equest-users mailing list