Dear All,
               I am modelling VRV unist as PVVT system but PVVT system is
giving lot of unmet hours if i change it to PVV system then my unmet hours
are controlled to the limits so can i go with PVV system for VRV.

Or how can i remove unmet hrs from PVVVT system any suggestions.