Yes - it can be a direct load on a hot water loop, an electric meter or a fuel meter depending on the source. You will need to create a fractional schedule of when the load is applied.
Brian Fountain
bfountain at greensim.com
-----Original Message-----
From: Zheng Ling <zling at williamsengineering.com>
Sender: equest-users-bounces at lists.onebuilding.org
Date: Thu, 3 Jan 2013 15:20:39
To: equest-users at lists.onebuilding.org<equest-users at lists.onebuilding.org>
Subject: [Equest-users] Snow melting system simulation