GK Pandian kgkpandian at gmail.com
Wed Jul 23 00:36:48 PDT 2014


Hi Pramod,



System reference PTHP or PSZ-HP should be referred only in baseline
model.  Your
proposed model should reflect your actual equipment type and capacity.  If
you have "Packaged terminal air conditioner" in your proposed design,then
you can change the proposed model to reflect the same.



*Thanks*

*S.Gopikumar LEED**®**AP BD+C*




On Wed, Jul 23, 2014 at 12:24 PM, Pramod .D <d.pramod at setty.com> wrote:

>  Hi Folks,
>
>
>
> I am modelling an apartment. For this I have air handling units with
> cooling type DX coils and heating type DX coil heat pump. I've modelled it
> as PSZ-HP in the proposed model and PTHP in the Baseline model. Now can I
> change in the proposed model to PTHP from PSZ-HP. If I do this I get
> savings. Is this appropriate? Your help will be greatly appreciated.
>
>
>
> Thanks and Regards,
>
> Pramod
>
>
>
> _______________________________________________
> Equest-users mailing list
> http://lists.onebuilding.org/listinfo.cgi/equest-users-onebuilding.org
> To unsubscribe from this mailing list send  a blank message to
> EQUEST-USERS-UNSUBSCRIBE at ONEBUILDING.ORG
>
>
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.onebuilding.org/pipermail/equest-users-onebuilding.org/attachments/20140723/f0bab454/attachment.htm>


More information about the Equest-users mailing list