Bachchulal,
   As is often the case, it is not really possible to know for sure 
without looking at the project but if you have defined schedules in 
TRNBuild, make sure you have defined two kinds of DAILY schedules: one 
for monday-friday and one for saturday-sunday. You then have to define a 
WEEKLY schedule and choose which DAILY schedule you want to use for each 
day of the week. If you have done all of that already then please send 
the *.tpf and *.b17 file to your distributor for assistance.
Kind regards,
  David


On 4/10/2014 01:20, Bachchulal Gupta wrote:
> DEAR ALL
> I am calculating the cooling load of a 5 zone building model make in 
> Tran Build
> schedule is given for cooling Monday-Friday 9-18 hrs , but it is 
> calculating the
> cooling load for weekend also .
> how this can rectify
>
> regards
> B.L.Gupta
>
>
> _______________________________________________
> TRNSYS-users mailing list
> TRNSYS-users at cae.wisc.edu
> https://mailman.cae.wisc.edu/listinfo/trnsys-users

-- 
***************************
David BRADLEY
Principal
Thermal Energy Systems Specialists, LLC
22 North Carroll Street - suite 370
Madison, WI  53703 USA

P:+1.608.274.2577
F:+1.608.278.1475
d.bradley at tess-inc.com

http://www.tess-inc.com
http://www.trnsys.com

-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.onebuilding.org/pipermail/trnsys-users-onebuilding.org/attachments/20140411/b5703c5c/attachment-0001.htm>


More information about the TRNSYS-users mailing list