[BLDG-SIM] eQUEST Preheat/Heating-Capacity in System Warning
Mitchell Dec
mdec at glumac.com
Tue Jun 7 12:14:00 PDT 2005
Hello All,
I have received the following error message from a model I am currently
working on in Portland, Oregon. The first floor is a veterinary clinic with
a single Packaged VAV System with 100% OA and ERV. I have checked the
inputs and loads as described at the end of the error warning without
obtaining a solution.
**WARNING*******************************************************************
***
PREHEAT/HEATING-CAPACITY in SYSTEM 1st Floor (RTU-1 VAV)
is too low to provide the requested supply temperature for
the calculated mixed air temperature using total ZONE loads
(on LS-A/B) and SYSTEM design parameters, plus outside air
conditions (on LS-C), and specified capacities & air flows.
Requested temperature is 55.00 calculated is 22.76
Check HEATING-CAPACITY, HEAT-SET-T, PRE-HEAT-T, MAX-SUPPLY-T,
DESIGN-HEAT-T, and ZONE loads for consistency.
Has anyone ever encountered this message? and if so, do you have any
suggestions as to how this can be resolved. This has caused a significant
cooling load increase and heating load decrease.
I would greatly appreciate any help that could aid me.
Thanks,
Mitchell J. Dec
Energy Analyst
503.345.6283 | mdec at glumac.com <mailto:mdec at glumac.com>
<http://www.glumac.com/> <?xml:namespace prefix = o ns =
"urn:schemas-microsoft-com:office:office" />
_____
320 SW Washington, Suite 200
Portland, OR 97204-2640
T. 503.227.5280 F. 503.274.7674
Thinking. Inside the building.
http://www.glumac.com/ <http://www.glumac.com/>
------------------
ATTACHMENT REMOVED
------------------
More information about the Bldg-sim
mailing list