I'm trying to Model a Munters DryCool unit within Equest. The
limitation I'm up against is that a Solid Desiccant wheel can only be
modeled as a preconditioner.
What I need is to :
1. Precool outside air with a DX coil to saturated air,
2. Run that saturated air through the Solid Desiccant, and
3. Finally run that air through a Cooling Coil served by a Chiller
before supplying to the space.
Ultimately is there a way to model a Desiccant after a DX coil instead
of a preconditioner?