[Bldg-sim] eQuest misc. Process load input
Xu, Xiaowei
xiaowei.xu at ny.fk.com
Thu May 1 06:29:49 PDT 2008
In Detailed Mode, choose Utility & Economics --> Electric Meters in the
component tree --> EM1 (double click) --> Direct Loads.
You can create a new schedule for the process loads.
Xiaowei Xu
Engineer
FLACK + KURTZ
475 Fifth Avenue, New York, NY 10017
Direct 212.951.2662
Email xiaowei.xu at ny.fk.com
________________________________
From: bldg-sim-bounces at lists.onebuilding.org
[mailto:bldg-sim-bounces at lists.onebuilding.org] On Behalf Of Josh
Greenfield
Sent: Thursday, May 01, 2008 9:24 AM
To: bldg-sim at lists.onebuilding.org
Subject: [Bldg-sim] eQuest misc. Process load input
In the Detailed Edit Mode of eQuest, how do I just put an annual misc.
process energy load value in the building to be included in the
simulation? (i.e., I've calculated the elevator usage for the year to
be X kWh...where do I put this now?? And do I have to define a schedule
for it to split it up across 365 days or will it do that
automatically??)
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.onebuilding.org/pipermail/bldg-sim-onebuilding.org/attachments/20080501/dc526b8f/attachment-0002.htm>
More information about the Bldg-sim
mailing list