[Bldg-sim] visual DOE system assignment

Gurneet Monga gurneet at edsglobal.com
Fri Apr 24 00:24:27 PDT 2009


Hi Ashraf,
Could you please mail more details about the model and clarify that are you
facing problem in making 20 new system or is it assigning one zone to
20 different system.

Regards

Gurneet Singh
Project Manager
Environmental Design Solutions
657 Sector A, Pocket C, Vasant Kunj-70



2009/4/19 ashraf khan <ashraf at mecsd.com>

>
>
> Hello All,
>
>
>
> I am working in Visual DOE. I am modeling a Cold Storage of 40,000sqft,
> which is conditioned, 20 HVAC systems are being used maintained by CHILLER.
>
>
>
> Can any one please tell me how to model 20 different systems in Visual DOE?
>
>
> Is I have to make single zone for one system or any other single system
> that is comparable.
>
>
>
> It will be helpful if you explain in details,
>
>
>
> Thanks & Regards,
>
>
>
> * Ashraf Ali Khan, LEED AP***
>
>  *Mechanical Engineer***
>
> * *
>
> P Please consider the environment before printing this email
>
>
>
>
>
>
>
> _______________________________________________
> Bldg-sim mailing list
> http://lists.onebuilding.org/listinfo.cgi/bldg-sim-onebuilding.org
> To unsubscribe from this mailing list send  a blank message to
> BLDG-SIM-UNSUBSCRIBE at ONEBUILDING.ORG
>
>
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.onebuilding.org/pipermail/bldg-sim-onebuilding.org/attachments/20090424/b6ce56c0/attachment-0002.htm>


More information about the Bldg-sim mailing list