Amandine,
We have had success (with a ventilated facade DSF configuration) using
an approach similar to what you're proposing. The challenge with it and
other configurations depends on the interaction of the DSF and the
building spaces. We coupled eQUEST, TRNSYS, COMIS, and wind tunnel test
data to achieve what seems to be a reasonable solution, especially for
the purposes of a cost analysis and LEED documentation.
Regards,
Paul
Paul Erickson
Sustainable Practice Leader
Affiliated Engineers, Inc
www.aeieng.com ( http://www.aeieng.com/ )
608.236.1112
303.859.7523 - c
>>> "Gal, Amandine" <Amandine.Gal at snclavalin.com> 8/5/2009 1:24 PM >>>
Dear all,
I am modelling a building with Equest and I would like to know as
Equest is not so efficient modelling passive system if I can use
EnergyPlus for the double-façade only and after add the results of E+ to
the one of Equest.
Thanks
Regards
Amandine Gal
Spécialiste en ingénierie
Division Transport, Infrastructures et Bâtiment
SNC-Lavalin inc.
8000 boul. Décarie, 3e étage
Montréal (Québec)
Canada H4P 2S4
Téléphone: 514-735-5651 poste 2346
Télécopieur: 514-737-7988
Courriel: amandine.gal at snclavalin.com (
blocked::mailto:amandine.gal at snclavalin.com )
www.snclavalin.com ( blocked::http://www.snclavalin.com/ )
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.onebuilding.org/pipermail/bldg-sim-onebuilding.org/attachments/20090805/0b4421b8/attachment-0001.htm>
More information about the Bldg-sim
mailing list