FYI...
You can do this with DOE-2 or EQUEST by cutting off the simulation at the SYSTEMS portion and summing
the chilled water and hot water that goes to PLANT. I believe you'll find the information you need in the
SS-D report for the total loads going to PLANT.
Jeff
8=! 8=) :=) 8=) ;=) 8=) 8=( 8=) :=') 8=) 8=) 8=?
Jeff S. Haberl, Ph.D., P.E.............................jhaberl at esl.tamu.edu
Professor......................................................Office Ph: 979-845-6507
Department of Architecture.......................Lab Ph: 979-845-6065
Energy Systems Laboratory.......................FAX: 979-862-2457
Texas A&M University..............................77843-3581
College Station, Texas, USA.......................URL: www-esl.tamu.edu
8=/ 8=) :=) 8=) ;=) 8=) 8=() 8=) 8=? 8=) 8=) 8=)
________________________________
From: bldg-sim-bounces at lists.onebuilding.org on behalf of Gregg Liddick
Sent: Mon 12/29/2008 9:53 AM
To: bldg-sim at lists.onebuilding.org
Subject: [Bldg-sim] Campus Chillers
I'm trying to figure out a way to model utility rates using a campus chiller. The building is billed by the ton of chilled water used. If anyone can help me find a way to do this it would be greatly appreciated.
Best Regards,
Gregg Liddick, LEED® AP
The Epsten Group, Inc.
429 Edgewood Avenue
Atlanta GA 30312
Phone: 404-577-0370 ext. 102
Fax: 404-577-1739
gliddick at theepstengroup.com
More information about the Bldg-sim
mailing list