Is that due to summer reheat? Healthcare facility requires somewhat high minimum air changes. So reheat may be needed in summer time.

Ming Zeng, PE, LEED(r) Accredited Professional
Mechanical Engineer

[http://mail2.leoadaly.com/ladlogorednl2.gif]
730 Second Avenue South, Suite 1100,  Minneapolis, MN 55402-2455
T 612.338.8741    F 612.338.4840    D 612.341.9539
www.leoadaly.com<http://www.leoadaly.com>    MZeng at leoadaly.com<mailto:MZeng at leoadaly.com>

EXCELLENCE BEYOND EXPECTATIONS
From: bldg-sim-bounces at lists.onebuilding.org [mailto:bldg-sim-bounces at lists.onebuilding.org] On Behalf Of Jay Kaiser
Sent: Monday, July 06, 2009 9:35 AM
To: bldg-sim at lists.onebuilding.org
Subject: [Bldg-sim] E-QUEST Heating Problems

All-

I am modeling a health care facility and for some reason the building is heating AND cooling during the summer months.  And because there is heating during summer, the cooling load increases greatly.  Does anybody know how this can be fixed?

Thanks,

Jay A. Kaiser
Energy Engineer
Focus on Energy
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.onebuilding.org/pipermail/bldg-sim-onebuilding.org/attachments/20090706/aed83d3b/attachment-0002.htm>