[Date Prev][Date Next][Thread Prev][Thread Next][Date Index][Thread Index]

Re: [EnergyPlus_Support] Irregular Scheduling





Look up CustomDay. You can create a schedule for a CustomDay1 or CustomDay2 and then schedule these days to occur when you want. You'll also need to include any extra day types in all your schedules.

--
Karen

On Friday, April 27, 2012, luke_dorna <luke.dorna@xxxxxxxxx> wrote:
>  
>
> All,
>
> I have a particular zone in my model that holds special after hours events twice a month. Does anyone have a nifty way to schedule a bi-monthly event in energy plus? Thanks,
>
> Luke
>
>

__._,_.___


Primary EnergyPlus support is found at:
http://energyplus.helpserve.com or send a message to energyplus-support@xxxxxxxx

The primary EnergyPlus web site is found at:
http://www.energyplus.gov

The group web site is:
http://groups.yahoo.com/group/EnergyPlus_Support/

Attachments are currently allowed but be mindful that not everyone has a high speed connection.  Limit attachments to small files.

EnergyPlus Documentation is searchable.  Open EPlusMainMenu.pdf under the Documentation link and press the "search" button.




Your email settings: Individual Email|Traditional
Change settings via the Web (Yahoo! ID required)
Change settings via email: Switch delivery to Daily Digest | Switch to Fully Featured
Visit Your Group | Yahoo! Groups Terms of Use | Unsubscribe

__,_._,___