[Equest-users] Process Loads
Steve Mignogna
smignogna at gmail.com
Tue Dec 16 09:25:45 PST 2008
Seth-
In the Equipment tab create an "internal energy source". Choose an
applicable schedule, then for source type, chose Gas. You can then assign
the Btu/hr and the sensible/latent heat fractions as well. Hope that does
the trick.
Cheers,
--
Steve Mignogna
Atelier Ten
On Tue, Dec 16, 2008 at 11:39 AM, Seth P. Spangler <sspangle at rmf.com> wrote:
> Hello All,
>
>
>
> I am having trouble finding where to edit the process energy for a zone in
> my model in detailed edit mode. The load is currently modeled as electric
> process load but I need to be a natural gas process load.
>
>
>
> Thank you in advance
>
>
>
> Seth Spangler, LEED(R) AP
>
> Design Engineer
>
>
>
>
>
> _______________________________________________
> Equest-users mailing list
> http://lists.onebuilding.org/listinfo.cgi/equest-users-onebuilding.org
> To unsubscribe from this mailing list send a blank message to
> EQUEST-USERS-UNSUBSCRIBE at ONEBUILDING.ORG
>
>
--
Steve Mignogna
Atelier Ten
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.onebuilding.org/pipermail/equest-users-onebuilding.org/attachments/20081216/675a3232/attachment-0002.htm>
More information about the Equest-users
mailing list