I am having a problem modeling a building which has a PVAV with a
pre-heat furnace and VAV electric reheat boxes. The pre-heat furnace is
intended to raise the temperature up to 55F while the heating is done
locally at the VAV electric reheat box. (This is where I have the
problem) At night (and weekend) the electric re-heat on the boxes are
shutoff and outside air is shut off. The building is set back in
temperature and heated via the preheat furnace. This is what I am
trying to find out:
1. Is there a way to schedule the electric reheat coils on the VAV
boxes?
2. Is there a way to shut off the outside air damper at
night/weekend?
Any help will be appreciated.
Thank you in advance,
ARTURO HERNANDEZ
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.onebuilding.org/pipermail/equest-users-onebuilding.org/attachments/20080903/d340b7c8/attachment.htm>
More information about the Equest-users
mailing list