[Equest-users] Total Run Hours
Rimes, Christie
Christie.Rimes at wspfk.com
Fri Aug 20 08:38:50 PDT 2010
Hi Connor,
Go To:
help-> tutorials and references -> Detailed Simulation Reports Summary
If you search for the SS-R report it says that the run hours are based
on the flow hours only. Therefore I am assuming that your fans are
running differently during their "off" time due to the "cycle on any"
fan control.
Cheers,
From: equest-users-bounces at lists.onebuilding.org
[mailto:equest-users-bounces at lists.onebuilding.org] On Behalf Of Jansen,
Connor
Sent: Thursday, August 19, 2010 10:57 AM
To: equest-users at lists.onebuilding.org
Subject: [Equest-users] Total Run Hours
Hello All,
Quick question for you. How are the total run hours summated in the SS-R
reports? I have two models baseline and proposed with the same fan
schedules however the run hours are different. I was under the
impression that the run hours are directly related to the times in which
the fans are scheduled off/on. Perhaps this is still the case and
something else has been altered between my runs. Thank you for the
clarification.
Regards,
Connor
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.onebuilding.org/pipermail/equest-users-onebuilding.org/attachments/20100820/99f600bd/attachment-0002.htm>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: not available
Type: image/png
Size: 10665 bytes
Desc: image001.png
URL: <http://lists.onebuilding.org/pipermail/equest-users-onebuilding.org/attachments/20100820/99f600bd/attachment-0002.png>
More information about the Equest-users
mailing list