Supplementary to John’s advice, you should take advantage of a new feature in 3.64 that lets you assign a prefix to the components of each of your shells to make your model more easily manageable in detailed.

 

If you have a “building A,” then you could clearly organize its generated zones/surfaces/schedules etc. by giving it a prefix of “BA,” for example (on the first DD shell screen, iirc).  For a hands-on example of this feature, seek out an eQuest importing guide I posted in the archives ;). 


~Nick

 

 

 

NICK CATON, E.I.T.

PROJECT ENGINEER

Smith & Boucher Engineers

25501 west valley parkway

olathe ks 66061

direct 913 344.0036

fax 913 345.0617

www.smithboucher.com 

 

From: equest-users-bounces at lists.onebuilding.org [mailto:equest-users-bounces at lists.onebuilding.org] On Behalf Of John Aulbach
Sent: Wednesday, December 08, 2010 11:05 AM
To: Yehuda Israel; eQuest
Cc: bfrank at newsource-energy.com; Hanan Waizman; howard at newsource-energy.com
Subject: Re: [Equest-users] boiler and chiller serving multiple buildings

 

Yehuda:

 

Yes, you certainly can have those seven shells. But you will also have the eighth shell where the central plant is. eQuest does not care where the plant is, but what is connected to it. Do no concern yourself with where the plant resides, but what is connected to it.

 

BTW, does the plant have its own electric and gas meters? You can worry about what meters go to what buildings in the Detailed Edit Mode, if you are trying to match bills.

 

This sounds like an interesting project, such as a campus or hospital complex.

 

John

 

________________________________

From: Yehuda Israel <Yehuda at NewSource-Energy.com>
To: John Aulbach <jra_sac at yahoo.com>; eQuest <equest-users at lists.onebuilding.org>
Cc: bfrank at newsource-energy.com; Hanan Waizman <hanan at newsource-energy.com>; howard at newsource-energy.com
Sent: Wed, December 8, 2010 7:25:27 AM
Subject: RE: [Equest-users] boiler and chiller serving multiple buildings

John

 

Thank you for your help.

 

I have a question on what you said.  The boiler and chiller that service the eight buildings are extremely big.  Anyway I have to start the model in the DD Wizard.  If I make eight different shells and show seven buildings without a boiler or chiller, it seems that I could 

 

From: John Aulbach [mailto:jra_sac at yahoo.com] 
Sent: Tuesday, December 07, 2010 7:06 PM
To: Yehuda Israel; eQuest
Cc: bfrank at newsource-energy.com; Hanan Waizman; howard at newsource-energy.com
Subject: Re: [Equest-users] boiler and chiller serving multiple buildings

 

Yehuda:

 

I surmise that all eight buildings are on the central plant with the chillers and boilers you describe. eQuest doesn't know that your 8 buildings are separate buildings, just more zones. I would describe your zones (in the Detailed Edit mode) such as "Building 1-North Zone" or "Building 8-Lobby" and put all the zones on one massive CHW and HHW loop.

 

You can also make these loops Secondary loops, if the Central Plant has its own loops.

 

Have fun !!

 

 

John R. Aulbach, PE, CEM

Senior Energy Engineer

________________________________

Partner Energy

1990 E. Grand Avenue, El Segundo, CA 90245
W: 888-826-1216, X254| D: 310-765-7295 | F: 310-817-2745

www.ptrenergy.com <http://wwwptrenergy.com/>  | jaulbach at ptrenergy.com <mailto:%7C%20jaulbach at ptrenergy.com> 

 

 

________________________________

From: Yehuda Israel <Yehuda at NewSource-Energy.com>
To: eQuest <equest-users at lists.onebuilding.org>
Cc: bfrank at newsource-energy.com; Hanan Waizman <hanan at newsource-energy.com>; howard at newsource-energy.com
Sent: Tue, December 7, 2010 8:46:42 AM
Subject: [Equest-users] boiler and chiller serving multiple buildings

To all:

 

I have a building complex consisting of 8 buildings.  In one of the buildings are the boiler and chiller that service all of the building through various pipes.  The other buildings don’t have their own boiler and chiller.  How do I model this into eQuest?

 

Thank you.

 

Yehuda Israel, 

Energy Analyst 

 

New Source Energy Group, Inc.

8 Ellington Way

New Hempstead, NY 10977

Main:    (845) 445-0457

Fax:      (845) 354-6347

www.NewSource-Energy.com <http://www.newsource-energy.com/> 

 

 

 

-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.onebuilding.org/pipermail/equest-users-onebuilding.org/attachments/20101208/51da4796/attachment-0002.htm>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: not available
Type: image/jpeg
Size: 1459 bytes
Desc: image001.jpg
URL: <http://lists.onebuilding.org/pipermail/equest-users-onebuilding.org/attachments/20101208/51da4796/attachment-0004.jpeg>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: not available
Type: image/jpeg
Size: 1535 bytes
Desc: image002.jpg
URL: <http://lists.onebuilding.org/pipermail/equest-users-onebuilding.org/attachments/20101208/51da4796/attachment-0005.jpeg>


More information about the Equest-users mailing list