I suggest using the layer-by-layer approach and the eQuest materials library
to ensure that you properly account for building mass and the associated
thermal response time lapse.  The U-value input assumes a generic
light-weight construction thermal response.  *Bonus* - the approach I
suggest is fun and easy!

Eric

Ph:   (781) 431-1100 ext 12
Fax:  (781) 431-1109
 

-----Original Message-----
From: equest-users-bounces at lists.onebuilding.org
[mailto:equest-users-bounces at lists.onebuilding.org] On Behalf Of Hind Dirani
Sent: Friday, February 12, 2010 9:30 AM
To: equest-users at lists.onebuilding.org
Subject: [Equest-users] External Building envelop

Dear all,

I'm trying to enter building envelop details to eQuest, it's better to
specify resistance value (to calculated U-value for walls), or specify
layer-by-layer.

Concerning the detailed section, most of walls consisting of:

1.       40cm wall (40cm concrete or 20cm concrete + 5cm void + 15cm HCB )

2.       15cm ventilated cladding system (5cm insulation + profiles + voids
+ Cladding)

any help is appreciated,


_______________________________________________
Equest-users mailing list
http://lists.onebuilding.org/listinfo.cgi/equest-users-onebuilding.org
To unsubscribe from this mailing list send  a blank message to
EQUEST-USERS-UNSUBSCRIBE at ONEBUILDING.ORG




More information about the Equest-users mailing list