Did you create a rate block, and then assign that block to a utility?
What did you input into the block?

 

When you go into your "custom elec rate," you should have the cost
either plugged into the energy/demand tab, or under the blocks tab. I
usually assign ratchets to individual blocks under "block charges" and
then assign these blocks to the electric utility.

 

________________________________

From: equest-users-bounces at lists.onebuilding.org
[mailto:equest-users-bounces at lists.onebuilding.org] On Behalf Of
mikef at facilitymgt.com
Sent: Thursday, July 22, 2010 4:46 PM
To: equest-users at lists.onebuilding.org
Subject: [Equest-users] BDL Error

 

I have set up rats for the local utility but when I use it I get an
error message. What I have used is 

BLOCKS-ARE   = INCREMENTAL

I get a BDL ERROR that says "Unknown Keyword or Previous .. Missing

How do I fix this? All of the information I have says for incremental
rates to use this, but if it is unknown what should I use?

Thanks 

 

Mike Freeman PE.

Facility Management & Engineering, Inc.

-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.onebuilding.org/pipermail/equest-users-onebuilding.org/attachments/20100722/85abeff9/attachment-0002.htm>


More information about the Equest-users mailing list