It's very likely that your bore-field is undersized. Make sure that your configuration is correct and that the multiplier against the bore configuration results in the number of bores you have in the field. Depth, conductivity, etc. also play a key role, but this is usually the reason I come across.

Depending on the actual configuration of the field you may also want to split the simulated field in two and have two GSHX fields to "draw" from.

Matthew Higgins, ASHRAE-HBDP, LEED-AP
Energy Engineer

Bridgers & Paxton Consulting Engineers, Inc.
4600-C Montgomery Blvd. NE
Albuquerque, NM  87109
505-883-4111
505-888-1436  Fax
mwhiggins at bpce.com

www.bpce.com

From: equest-users-bounces at lists.onebuilding.org [mailto:equest-users-bounces at lists.onebuilding.org] On Behalf Of Christian Stalberg
Sent: Friday, May 28, 2010 6:52 AM
To: equest-users at lists.onebuilding.org
Subject: [Equest-users] GSHP supp. heat & unmet hours

I have a building using a GSHP with electric supplemental heating
and I'm getting almost 30% unmet heating hours. Any ideas why
this could be occuring?
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.onebuilding.org/pipermail/equest-users-onebuilding.org/attachments/20100528/ee720c1d/attachment-0001.htm>


More information about the Equest-users mailing list