Anura,
It depends on how large your building is and which version of ASHRAE
you're using. For ASHRAE 90.1-2004, the baseline should have one
system per thermal zone (even if you're proposed model is set up
differently). If you're in ASHRAE 90.1-2007, up to a certain size
building, it's still one system per thermal zone. After the threshold
size, you're supposed to do one system for each floor of the building.
I think the threshold size is 150,000 sq ft, but double check App.G to
be sure.
Kristy
Be Green! Sent from my iPhone.
On Jul 23, 2011, at 12:53 AM, "anura perera"
<perera.anura25 at gmail.com> wrote:
> Dear All,
>
> I am modeling a Hotel in eQUEST for which the baseline HVAC system
> type is PTHP. My proposed system has AHUs & FCs supplied by a
> secondary pump circuit using chilled water.
>
> Can anyone indicate to me as to how I should plce my baseline system
> (i.e on the basis of site, floor or thermal zones). The obvious
> choice is thermal zones as per the proposed design.
>
> Thanks in adavnce
>
> Anura
> _______________________________________________
> Equest-users mailing list
> http://lists.onebuilding.org/listinfo.cgi/equest-users-onebuilding.org
> To unsubscribe from this mailing list send a blank message to EQUEST-USERS-UNSUBSCRIBE at ONEBUILDING.ORG
More information about the Equest-users
mailing list