[Equest-users] chiller sequencing
Fleming, Joe
joe.fleming at tlc-eng.com
Thu Mar 3 11:58:17 PST 2011
How would one sequence chillers in the following way?
Chiller 1 - up to 150 tons
Chiller 2 - 150-350 tons (Chiller 1 is off in this range)
Chiller 1&2 - 350-500 tons
The Load range tab provides a "max load", but I believe that when I move to step 2 that equest is going to keep both chillers on.
i.e. for an input such as;
Chiller-Seq-Max Load
Chiller 1 - 1 - 150
Chiller 2 - 2 - 350
Should you utilize the different "Load Ranges" here?
The help file for this sections is not as robust as the other help sections.
Thank You
Joe Fleming
E.I., LEED AP BD+C, BEMP
Mechanical Engineer II
TLC Engineering for Architecture
Your 2030 Challenge Partner
800 Fairway Drive, Suite 250
Deerfield Beach, FL 33441-1816
phone:
954-418-9096
fax:
954-418-9296
direct:
954-418-4591
website:
www.tlc-engineers.com<http://www.tlc-engineers.com/>
[cid:image001.gif at 01CBD9B2.FBA742C0]<http://www.tlc-engineers.com/>
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.onebuilding.org/pipermail/equest-users-onebuilding.org/attachments/20110303/df812cf9/attachment.htm>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image001.gif
Type: image/gif
Size: 5272 bytes
Desc: image001.gif
URL: <http://lists.onebuilding.org/pipermail/equest-users-onebuilding.org/attachments/20110303/df812cf9/attachment.gif>
More information about the Equest-users
mailing list