[Equest-users] Request for Clarification on PTAC

anura perera perera.anura25 at gmail.com
Mon May 16 19:21:16 PDT 2011


Dear All,

As per the Appendix G requirement, for my project, the Basecase HVAC system
has to be system type- 2 which is Package Terminal Heat Pump, DX Cooling,
Electric Heating. (from Appendix G)

When this is selected from the appropriate menu and the simulations are
done, the output file indicates the system type as PTAC. This usually stands
for Packaged Terminal AC. In principle it can also mean Packaged terminal
Heat Pump as AC is also a Heat Pump.

Can PTAC be taken as to mean Packeged Terminal Heat Pump as well as given in
the output file or is eQUEST performing something starnge ??

Thanks in advance for any clarification

Anura