Hello,
I am having some issues on a EPAct project with HVAC Equipment. The Quality
Check Details states that My CFM/ton of Cooling is high at around
750cfm/ton. I have entered the exact design flows/ sizes of the heat pumps
as indicated in the mechanical schedules, but something seems to be short
circuiting the heating/ cooling relationship. Should I discard the actual
supply flow rate? I guess the real question stems from the fact that when I
increase the sizing of the system above 1.0 to ~1.25, the heating actually
gets worse. Same thing with specifying airflow zone by zone. At this
point, it seems that there is something obvious I am overlooking.
thanks,
nic
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.onebuilding.org/pipermail/equest-users-onebuilding.org/attachments/20111011/3fc76c4c/attachment.htm>
More information about the Equest-users
mailing list