Dan, eQUEST lets you specify infiltration using the following methods.

   - Air changes per hour (ACH)
   - CFM per square foot of conditioned floor area
   - CFM per square foot of exterior wall area

You can input this here in screen 3 of the building shell components dialog
of the design development wizard. You have the option of setting an
infiltration schedule in the component tree of the detailed data edit mode.
A schedule name will look like "ZG0-S1 (PSZ) P-Inf Sch" and "...C-Inf Sch"
depending on your method. Be sure to "view detailed simulation output file"
after you run a simulation to check LS-B, LS-C reports to see if the
infiltration load component is reasonable.








*Arpan Bakshi**    *LEED AP BD+C, ESTIDAMA PQP



On Fri, Aug 3, 2012 at 3:58 PM, Daniel Sze <dsze314159 at gmail.com> wrote:

> Good afternoon,
>
> I have started to use eQuest as a part of my job and I need to model air
> infiltration in eQUEST as prescribed in the  2005 Nonresidential ACM Manual
> (2.4.1.6). However, since I am still relatively new to the program, I still
> am not quite sure how to model the air infiltration.
>
> Can you guys help me?
>
> Thank you in advance.
>
> _______________________________________________
> Equest-users mailing list
> http://lists.onebuilding.org/listinfo.cgi/equest-users-onebuilding.org
> To unsubscribe from this mailing list send  a blank message to
> EQUEST-USERS-UNSUBSCRIBE at ONEBUILDING.ORG
>
>
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.onebuilding.org/pipermail/equest-users-onebuilding.org/attachments/20120803/33fc17ca/attachment-0001.htm>


More information about the Equest-users mailing list