[Equest-users] Steam Traps

R B slv3sat at gmail.com
Thu May 10 10:21:31 PDT 2012


I have done is as process load - if the estimate is that 5-10% of the
heating is because of this, I iterated a few times - do not remember what I
did for schedule.
-Rohini
On Thu, May 10, 2012 at 10:32 AM, Jeremy Poling <jeremy.poling at att.net>wrote:

> I thought this had been asked before but was unsuccessful bringing it up
> in the archives.
>
> For a steam baseboard system, is there a way to model a loss factor due to
> faulty steam traps?  I could see using the SUPPLY-LOSS-DT keyword as a
> means to model this, but my input there would be based on a guess at the
> system loss due to the steam trap.
>
> This is for a calibrated model, as an FYI.  Thanks!
>
> Jeremy R. Poling, PE, LEED AP+BDC
> Sustainability Consultant
>
>
> _______________________________________________
> Equest-users mailing list
> http://lists.onebuilding.org/listinfo.cgi/equest-users-onebuilding.org
> To unsubscribe from this mailing list send  a blank message to
> EQUEST-USERS-UNSUBSCRIBE at ONEBUILDING.ORG
>
>
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.onebuilding.org/pipermail/equest-users-onebuilding.org/attachments/20120510/8e75cc89/attachment-0002.htm>


More information about the Equest-users mailing list