[Equest-users] VAV with electric heat
Pasgar, Arash
APasgar at dbrinc.com
Mon Sep 10 13:07:20 PDT 2012
Dear all,
I still couldn't finish my model.
I put zone heat source as electric.
Try different zone entering max supply temp, hot deck max leaving temp, and reheat delta t.
I put my exact heating capacity base on my VAV schedule under heating capacity for each zone.
But nothing works.
I can control unmet hours but I have got almost 850 warning error like:
Zone: Reception-A117 could not successfully
allocate all equipment energy to the 5-minute bins
because of an equipment overload. The peak load
used in ECONOMICS will not include the fraction due
to the overload, but the PLANT reports will.
Mon/Day/Hour: 1 3 7 Energy: 1.3 Unallocated: 0.065
I really need to finish this model soon.
Thank you for your help
Arash Pasgar
Mechanical Designer
[Description: Description: Description: Description: Description: Description: image001]
v. 210.546.0200 | www.dbrinc.com
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.onebuilding.org/pipermail/equest-users-onebuilding.org/attachments/20120910/b32f31ad/attachment.htm>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image002.jpg
Type: image/jpeg
Size: 4870 bytes
Desc: image002.jpg
URL: <http://lists.onebuilding.org/pipermail/equest-users-onebuilding.org/attachments/20120910/b32f31ad/attachment.jpg>
More information about the Equest-users
mailing list