[Equest-users] How the get the "estimated load profile"?

David Griffin dgriffin at etcgrp.com
Tue Apr 16 13:20:48 PDT 2013


Esmireta,

It has been awhile since I modeled a central plant for a LEED project, so you'll have to verify my comments.

After applying a CHW meter and a Steam Meter to your CHW Loop and HW Loop respectively, a new Central Plant can be modeled in either of the following ways:


1)    Using efficiencies per section 2.4.1.2.3 Default Efficiencies and applying them to your meters, or

2)    Using efficiencies per the design specifications and applying them to your meters.

I don't remember ever seeing a 'process load' that must be applied to the plant. I'm sure some else will chime in a correct me if I'm wrong. Have a great day!

Thanks,

David Griffin
Energy Analyst
ETC Group, LLC
801.278.1927 ext. 128
Cell 480.235.0899
Fax 801.486.0668
dgriffin at etcgrp.com<mailto:dgriffin at etcgrp.com>

[Copy of ETC_LogoOnly2_rgb_sm.png]
1997 South 1100 East, Suite 201, Salt Lake City, UT 84106-4471 - www.etcgrp.com<http://www.etcgrp.com/>
-------------------------------------------------------------------------------------------------------------------
CONFIDENTIALITY NOTICE This e-mail transmission, and any documents, files or previous e-mail messages attached to it may contain confidential information that is legally privileged.  If you are not the intended recipient or the person responsible for delivering it to the intended recipient, you are hereby notified that any disclosure, copying, distribution or use of any of the information contained in or attached to this transmission is strictly prohibited.  If you have received this transmission in error, please immediately notify us by telephone at (801) 278-1927 and destroy the original transmission and its attachments without reading them. Thank you.

From: Esmireta [mailto:e2fye2 at 163.com]
Sent: Monday, April 15, 2013 7:49 PM
To: BLDGSIM; equest-users
Subject: [Equest-users] How the get the "estimated load profile"?

Dear all,
When simulating district cooling for LEED, a virtual plant is required to be added to the proposed building, according to the "Treatment of District or Campus Thermal Energy in LEED V2 and LEED 2009 - Design & Construction".
The efficiency of the virtual plant is obtained through modeling if the district cooling system is new.
The "Treatment of District or Campus Thermal Energy in LEED V2 and LEED 2009 - Design & Construction" said, "Apply measured or estimated load profiles as "process loads" to reflect the estimated total loads on the district energy plant".
My question is:
What is the estimated load? If the district cooling system provides cold to any other buildings that are not in the LEED certificate scope, how can I get the estimated load?
Regards,
Esmi

-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.onebuilding.org/pipermail/equest-users-onebuilding.org/attachments/20130416/ac5a3386/attachment-0001.htm>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image001.jpg
Type: image/jpeg
Size: 1559 bytes
Desc: image001.jpg
URL: <http://lists.onebuilding.org/pipermail/equest-users-onebuilding.org/attachments/20130416/ac5a3386/attachment-0002.jpg>


More information about the Equest-users mailing list