[Equest-users] Building Geometry

Nick Caton ncaton at smithboucher.com
Wed Apr 9 06:52:23 PDT 2014


I see a few paths forward, of varying complexity:


-          Are you comfortable assuming the double height shades are static, or do you want to define them with a fractional annual shading schedule? (the former can be accomplished in wizards with 2 window types, the latter requires detailed edits)

-          Are you comfortable with massaging the interior zone layouts such that both floors have identical footprint?  If so, that also simplifies things much further geometrically and the geometries can be done largely within the wizards.

-          I think any approach will require detailed edits to switch the 2nd level office partitions (glazing) to something thermally representative of glass.

-          If neither above simplification is acceptable, you can either define 2 shells, one for each level, or 3 nested shells (perimeter donut, core first level, core 2nd level).  Each of these approaches requires a fair amount of post-wizard geometrical edits.  If you aren't comfortable with detailed mode geometrical edits, factor that into your decision as to whether the "identical zone layout" simplification is acceptable.

Also this may be obvious, but in case you weren't aware, Katia L. opened a thread here for the same building with specific regard to how one might approach the roof geometrically.

~Nick

[cid:489575314 at 22072009-0ABB]

NICK CATON, P.E.
SENIOR ENGINEER

Smith & Boucher Engineers
25501 west valley parkway, suite 200
olathe, ks 66061
direct 913.344.0036
fax 913.345.0617
www.smithboucher.com

From: equest-users-bounces at lists.onebuilding.org [mailto:equest-users-bounces at lists.onebuilding.org] On Behalf Of Elie Ayoub
Sent: Wednesday, April 09, 2014 4:08 AM
To: equest-users at lists.onebuilding.org
Subject: [Equest-users] Building Geometry

Dear All,

Please advice how can we define the space attached in the pics using eQUEST
I am dealing with a two storey office and want to define its geometry in eQUEST
I tried to use the AutoCAD drawing but eQUEST wasn't reading it properly
I have Double Glazing for the upper office floor with a void between them. This Void is connected to the lower office space as you can see from the attachments
Please help so I would be able to perform the energy modeling on this Project

Best Regards

Elie Ayoub
Assistant Project Engineer
OPUS consulting engineers - Mechanical Department
www.opus-engineering.com<mailto:zhaddad at opus-engineering.com>
+961 / T: (0)1 381360 - F: (0)1 381356
[http://www.docbert.org/blog/pics/P-Webding.png]Please consider the environment before printing this email



__________ Information from ESET NOD32 Antivirus, version of virus signature database 9653 (20140408) __________

The message was checked by ESET NOD32 Antivirus.

http://www.eset.com
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.onebuilding.org/pipermail/equest-users-onebuilding.org/attachments/20140409/cdddb49f/attachment-0002.htm>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image002.jpg
Type: image/jpeg
Size: 1459 bytes
Desc: image002.jpg
URL: <http://lists.onebuilding.org/pipermail/equest-users-onebuilding.org/attachments/20140409/cdddb49f/attachment-0002.jpg>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image003.png
Type: image/png
Size: 1117 bytes
Desc: image003.png
URL: <http://lists.onebuilding.org/pipermail/equest-users-onebuilding.org/attachments/20140409/cdddb49f/attachment-0002.png>


More information about the Equest-users mailing list