Sorry! I plan on assigning the zone groupings anyway which will supersede the HVAC assignments but I'm just wondering how this would normally be done.

I currently have one air-side system (the default HVAC System 1).

[cid:image003.jpg at 01CF65FE.97ABF000]

I want the current air-side system (HVAC System 1) to apply only to shell 4 and 5.  I want the other shells to apply to a new system.

But when I create a new system for shells 1,2,3  I then can't go back and remove those shell components in green from "HVAC System 1".
(Under System Assignment to Thermal Zones).

[cid:image004.jpg at 01CF65FE.97ABF000]

By default all shells are listed in "HVAC System 1".  From what I can tell there is now way to create a new air-side system and then remove shell components from the original "HVAC System 1".

It will let me add Shell 1,2,3 to the new system but it won't let me remove shells 1,2,3 from the other system - if that makes sense.

In other words some zones end up being listed on both systems with no way to remove them where I need to.

Not an issue for modeling since the zone grouping supersedes this but it just seems odd that I can select a system per shell but cannot remove a shell listed in green if it doesn't apply to said system.

Is there a way to do this that I'm overlooking?

Chris Baker
CCI CAD Drafter

From: Brian Fountain [mailto:bfountain at greensim.com]
Sent: Wednesday, April 30, 2014 6:46 PM
To: Chris Baker
Cc: equest-users at lists.onebuilding.org
Subject: RE: DD Wizard - Air-side System Type Question

I am not sure that I fully understand what is happening but will take a stab at helping anyway (which is always dangerous).

There are 2 places in the DD wizard you can assign portions of a building to different air-side HVAC systems: the 1st screen of the air-side HVAC definition (I ignore this), and screen 14 of each Shell - the zone grouping screen.  What you can do in the 1st screen of the HVAC is limited and is superceded by screen 14 - the zone grouping of the shells.

So, my practise is to:

1)      Define separate zone groups for different HVAC systems in the shells definition (if all zones in a shell are the same HVAC system, that's fine)

2)      Define all the air-side HVAC system types

3)      Go back to the zone grouping screen (DD wizard shell screen 14) for each shell and assign the HVAC system for each of the zone groups in that shell.

I hope this helps - let me know if I missed the mark.

Cheers,
BF

From: Chris Baker [mailto:CBaker at cci-alliance.com]
Sent: Wednesday, April 30, 2014 9:10 PM
To: equest-users at lists.onebuilding.org<mailto:equest-users at lists.onebuilding.org>; Brian Fountain (bfountain at greensim.com<mailto:bfountain at greensim.com>)
Subject: DD Wizard - Air-side System Type Question

So I have a building with 5 shell components all listed in the project navigator.

Shells 1,2,3 have an HRV system (air-side)

Shells 4,5 have an HVAC system with vav box and reheat coils (air-side)

I want my system per area assignment to be "System per Shell".  So it should be organized as such.

However, for some reason it keeps showing all shells on the default "HVAC System 1" (in green text) and they cannot be removed from the list and then added to the other air-side system.

All I want to do is split the shells into two different air-side systems but it automatically compiles all shells into the first (original) HVAC system 1.  If I change the green text to "undefined" it defaults back to the original shell and is therefore unchangeable.

When I create the "new" HRV air side system it doesn't show any shells assigned.  It will let me choose whatever shells I want but I then can't remove those shells from the other (HVAC) system - if that makes sense.

What am I missing here?

I'm still in the process of Grouping my zones because the project manager is working on getting me the information regarding space allocation (Sheet 13 I believe in DD wizard).

Does the zone grouping need to be done before I add a second air-side system?

I've tried adding shells 1,2,3 to the HRV system (the new one) and then removing the green text for those shells from "HVAC System 1" but it just doesn't work.

Any help is appreciated.  Thank you.

Chris Baker
CCI CAD Drafter


________________________________
CCI-Alliance Confidentiality notice: This message is intended only for the person to whom addressed in the text above and may contain privileged or confidential information. If you are not that person, any use of this message is prohibited. We request that you notify us by reply to this message, and then delete all copies of this message including any contained in your reply. Thank you.

________________________________
CCI-Alliance Confidentiality notice: This message is intended only for the person to whom addressed in the text above and may contain privileged or confidential information. If you are not that person, any use of this message is prohibited. We request that you notify us by reply to this message, and then delete all copies of this message including any contained in your reply. Thank you.
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.onebuilding.org/pipermail/equest-users-onebuilding.org/attachments/20140502/f5d748fd/attachment-0002.htm>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image003.jpg
Type: image/jpeg
Size: 20144 bytes
Desc: image003.jpg
URL: <http://lists.onebuilding.org/pipermail/equest-users-onebuilding.org/attachments/20140502/f5d748fd/attachment-0004.jpg>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image004.jpg
Type: image/jpeg
Size: 26286 bytes
Desc: image004.jpg
URL: <http://lists.onebuilding.org/pipermail/equest-users-onebuilding.org/attachments/20140502/f5d748fd/attachment-0005.jpg>


More information about the Equest-users mailing list