[BLDG-SIM] ASHRAE 90.1 and Energy Cost Budget Method budget building
Brian Thornton
thorntonenergy at comcast.net
Mon Aug 15 09:08:08 PDT 2005
The 90.1 rules provide explicit guidance on modeling by modifying the
proposed design per the rules in the ECBM and exclude anything not
explicitly in those rules.
According to the 90.1-1999 User's Manual, but not obviously in the text of
ASHRAE 90.1-1999, it is also necessary to add to the baseline all
prescriptive path features not modeled in the proposed design and not
spelled out in the Budget Building rules in 90.1-1999. .
Am I overlooking something in the text of ASHRAE 90.1-1999, or is this
requirement only in the narrative introduction of the ECBM section of the
90.1-1999 User's Manual?
I also don't see this requirement explicitly in the ASHRAE 90.1-2004 text on
the ECBM.
Any thoughts?
Thornton Energy Consulting
p. 503-231-6600 f. 503-231-3555
thorntonenergy at comcast.net
======================================================
You received this e-mail because you are subscribed
to the BLDG-SIM at GARD.COM mailing list. To unsubscribe
from this mailing list send a blank message to
BLDG-SIM-UNSUBSCRIBE at GARD.COM
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.onebuilding.org/pipermail/bldg-sim-onebuilding.org/attachments/20050815/cd004ea9/attachment.htm>
More information about the Bldg-sim
mailing list