[BLDG-SIM] eQuest warning
smorgan at noresco.com
smorgan at noresco.com
Thu Jun 16 07:21:40 PDT 2005
Does anyone know how to rectify this eQuest warning?
Zone: EL1 East Perim Zn (G.E3)could not successfully
allocate all equipment energy to the 5-minute bins
because of an equipment overload. The peak load
used in ECONOMICS will not include the fraction due
to the overload, but the PLANT reports will.
Mon/Day/Hour: 1 3 8 Energy: 2.5 Unallocated: 0.310
===========================
You received this e-mail because you are subscribed
to the BLDG-SIM at GARD.COM mailing list. To unsubscribe
from this mailing list send a blank message to
BLDG-SIM-UNSUBSCRIBE at GARD.COM
-------------- next part --------------