Hi-
In the PS-C report (sim file), the annual heating load for the boiler is
almost two-third the annual fuel use (in MBtu).
I'm assuming that ventilation load is the difference between the heating
loads from PS-C and LS-F, so PS-C should have ventilation included. Correct
me if 'm wrong.
The boiler heat load is 1940 MBTU and the Fuel use is 3100 MBTU (PS-C).
Applying, 84% boiler efficiency to heat load should give me 2308 MBTU (i.e.,
1940* 1.19).
So where am I getting that extra 800 MBTU from?
Any feedback appreciated.
--
Vämshi Goojè
===========================
You received this e-mail because you are subscribed
to the BLDG-SIM at GARD.COM mailing list. To unsubscribe
from this mailing list send a blank message to
BLDG-SIM-UNSUBSCRIBE at GARD.COM
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.onebuilding.org/pipermail/bldg-sim-onebuilding.org/attachments/20050615/1eae8562/attachment.htm>
More information about the Bldg-sim
mailing list