Dear folks,
I am always confused which report I shall use to count unmet load hours. The
under-cooled or heated hours to be summed in the SS-R is different from
PERCENT OF HOURS ANY SYSTEM ZONE OUTSIDE OF THROTTLING RANGE to be
multiplied by 8760 hours.
Please advise which numerb I shall use to fill in the LEED EA Cr1 template.
Thanks a lot.
Jessi