[Bldg-sim] Which report is used for unmet load hours, SS-R or BEPS?

Steve Mignogna smignogna at gmail.com
Mon Mar 24 10:23:01 PDT 2008


this question was just answered.  see the archive.

On Sun, Mar 23, 2008 at 12:22 PM, Jessica XP <xupingjessica at gmail.com>
wrote:

> Dear folks,
>
> I am always confused which report I shall use to count unmet load hours.
> The under-cooled or heated hours to  be summed in the SS-R is different from
> PERCENT OF HOURS ANY SYSTEM ZONE OUTSIDE OF THROTTLING RANGE to be
> multiplied by 8760 hours.
>
> Please advise which numerb I shall use to fill in the LEED EA Cr1
> template.
>
> Thanks a lot.
>
> Jessi
> _______________________________________________
> Bldg-sim mailing list
> http://lists.onebuilding.org/listinfo.cgi/bldg-sim-onebuilding.org
> To unsubscribe from this mailing list send  a blank message to
> BLDG-SIM-UNSUBSCRIBE at ONEBUILDING.ORG
>
>


-- 
Steve Mignogna
Atelier Ten
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.onebuilding.org/pipermail/bldg-sim-onebuilding.org/attachments/20080324/95a055ed/attachment-0002.htm>


More information about the Bldg-sim mailing list