Hello All,

 

I am in the planning stage of modeling a campus boiler plant. I have two
questions as follows:

 

1)       ASHRAE/LEED require a minimum process energy of 25% of the
total building energy. I am predicting that my plant (15 boilers plus
pumps etc.) process load will be 95% of my buildings energy use if not
more. Is there a way to reduce the process energy use of the plant for
energy modeling purposes other than an exceptional calculation method? 

2)       Is this a situation where I could perform an exceptional
calculation and compare a "standard" boiler plant to the high efficiency
one that is being installed?

 

Thanks in advance for your help.

 

Seth Spangler, LEED(r) AP 

Design Engineer

 

RMF Engineering, Inc 

Ph: (843) 971-9639 ext:108

Fax: (843) 971-9641 

sspangle at rmf.com

 

-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.onebuilding.org/pipermail/bldg-sim-onebuilding.org/attachments/20080520/a5c84521/attachment.htm>


More information about the Bldg-sim mailing list