Hi Omer

Precision coolers/ACs in server rooms should not be counted under process
energy but if your baseline case HVAC system type is 5, 6, 7 or 8 (Table G
3.1.1A) you can model a separate HVAC system type for server rooms as per
exceptions to G3.1.1. This could be either system 3 or 4.

Regards

On 19 February 2010 02:09, <omoltay at mimtarch.com> wrote:

> Dear All,
>
> Would you consider precision coolers in server rooms to be process energy?
> This is how I would like to apply in my model for LEED EAc1 (essentially
> not modelling any precision coolers and dumping it away under the default
> 25% value for process energy). Any opinions?
>
> Thank you,
>
> Omer Moltay, LEED AP
>
> _______________________________________________
> Bldg-sim mailing list
> http://lists.onebuilding.org/listinfo.cgi/bldg-sim-onebuilding.org
> To unsubscribe from this mailing list send  a blank message to
> BLDG-SIM-UNSUBSCRIBE at ONEBUILDING.ORG
>


Regards

-- 
Hisham Ahmad

Energy Analyst
Environmental Design Solutions Pvt Ltd.
New Delhi, India
+91-9873065488
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.onebuilding.org/pipermail/bldg-sim-onebuilding.org/attachments/20100219/b92728b8/attachment-0001.htm>


More information about the Bldg-sim mailing list