25% is the suggested minimum process energy use - the actual process use should be modeled, even if greater than 25%.
-DSE
http://www.grummanbutkus.com
On Feb 19, 2010, at 12:14 AM, "Hisham Ahmad" <hisham at edsglobal.com<mailto:hisham at edsglobal.com>> wrote:
Hi Omer
Precision coolers/ACs in server rooms should not be counted under process energy but if your baseline case HVAC system type is 5, 6, 7 or 8 (Table G 3.1.1A) you can model a separate HVAC system type for server rooms as per exceptions to G3.1.1. This could be either system 3 or 4.
Regards
On 19 February 2010 02:09, <<mailto:omoltay at mimtarch.com>omoltay at mimtarch.com<mailto:omoltay at mimtarch.com>> wrote:
Dear All,
Would you consider precision coolers in server rooms to be process energy?
This is how I would like to apply in my model for LEED EAc1 (essentially
not modelling any precision coolers and dumping it away under the default
25% value for process energy). Any opinions?
Thank you,
Omer Moltay, LEED AP
_______________________________________________
Bldg-sim mailing list
<http://lists.onebuilding.org/listinfo.cgi/bldg-sim-onebuilding.org>http://lists.onebuilding.org/listinfo.cgi/bldg-sim-onebuilding.org
To unsubscribe from this mailing list send a blank message to <mailto:BLDG-SIM-UNSUBSCRIBE at ONEBUILDING.ORG> BLDG-SIM-UNSUBSCRIBE at ONEBUILDING.ORG<mailto:BLDG-SIM-UNSUBSCRIBE at ONEBUILDING.ORG>
Regards
--
Hisham Ahmad
Energy Analyst
Environmental Design Solutions Pvt Ltd.
New Delhi, India
+91-9873065488
_______________________________________________
Bldg-sim mailing list
http://lists.onebuilding.org/listinfo.cgi/bldg-sim-onebuilding.org
To unsubscribe from this mailing list send a blank message to <mailto:BLDG-SIM-UNSUBSCRIBE at ONEBUILDING.ORG> BLDG-SIM-UNSUBSCRIBE at ONEBUILDING.ORG<mailto:BLDG-SIM-UNSUBSCRIBE at ONEBUILDING.ORG>
More information about the Bldg-sim
mailing list