Hello All,
I am trying to model a three floor office building for LEED V3. The first
and second floor are served by two chilled water air handlers, both
manifolded and running in parallel.
Does LEED require to model both the units because the schedules and drawings
show two units.
For baseline, I know ASHRAE G3.1.1 states I have to have seperate HVAC
system for each floor, as I have system 5.
--
Thanks and Best Regards,
Sincerely,
Varun Kulkarni , M.S. , EIT
RMF Engineering
5520, Research Park Drive, Suite 300
Baltimore, MD - 21228
Office : 410-576-0505 ext. 5352