I'm at the planning stage for a LEED NC v 2009 compliance model. The
building is a university gymnasium with a main gym and two practice gyms.
The facility also contains locker rooms, a weight room, a sports medicine
area, offices, classrooms, and circulation spaces. The building has two
floors above grade, plus a basement mechanical room, with a floor area of
roughly 90,000 SF. Most of the facility is gymnasium space, the other
("non-predominant") uses do not individually total over 20,000SF in area.
The heating source is a campus steam loop fed by a central plant with
natural gas-fired steam boilers. Cooling is by a campus chilled water loop.
Based on G3.1.1 and table G3.1.1A, the required LEED baseline HVAC system
will be System 5-Packaged VAV with Reheat - DX cooling and Hot-water fossil
fuel boiler.
My read on this is that, for the LEED baseline, I will have two separate
system 5's, one for each floor, with a unit heater for the basement mech
room. Since the campus has central heating and cooling, do I use those
systems to provide heating & cooling sources for the LEED baseline, or do I
use DX cooling and a hot water fossil fuel boiler per table G3.1.1B?
Thanks in advance.
Steven
Steven Savich, LEED AP
Systems West Engineers
411 High Street
Eugene, OR 97401-2427
(541) 342-7210
(541) 342-7220 (fax)
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.onebuilding.org/pipermail/bldg-sim-onebuilding.org/attachments/20121009/49c464a1/attachment.htm>
More information about the Bldg-sim
mailing list